A remodel bid is only as good as the measurements under it. Here is how to go from a measured floor plan to a room-by-room estimate: scope, quantities, allowances, contingency, and overhead and profit.

vPlan AR Team

vPlan AR

Most remodel bids that lose money don't lose it on the rate for tile or drywall. They lose it on quantities: a wall measured short, a closet left out, trim counted from memory. A bid written from a measured floor plan starts from the real sizes of every room, so the numbers you price are the numbers the crew will install.

This guide walks through a remodel estimate the way an estimator builds one: measure the space, write the scope room by room, take each quantity from the measurements, add allowances and job costs, then contingency, overhead and profit. It ends with a worked bathroom and how the same steps look in vPlan AR.

Start from a Measured Plan

Measure every room the work touches, plus the rooms you'll walk materials through. For each one you need the floor outline, the ceiling height, and every door and window with its width and height, because openings come off wall area and doorways come off trim.

A LiDAR scan on an iPhone Pro or iPad Pro captures all of that in one walk; on other phones you can measure room by room with the camera and check a wall with a tape, or draw the rooms from tape measurements. Whichever way you measure, the plan is the single source of quantities for everything that follows. See how to measure a room with your phone.

Write the Scope Room by Room

Write down what the client wants in each room in plain words before you price anything: "remove vanity and toilet, tile the floor, new 36-inch vanity, paint walls and ceiling". This is the work requested, and it is what the client will read when they compare bids.

Then turn each request into lines in the order the work happens: demolition and protection, rough-in (framing, plumbing, electrical), close-up (drywall), finishes (tile, flooring, paint, trim), then fixtures and cabinets. Writing it in that order makes missed steps obvious, such as a new vanity location that needs the drain moved.

Take Quantities from the Measurements

Each line's quantity should come from the room, not from a guess. Estimators use a short set of room measurements for this, the same abbreviations you'll see on insurance estimates: F for floor area, C for ceiling area, W for wall area less doors and windows, WC for walls plus ceiling, PF for the floor perimeter and H for the ceiling height. Our guide to estimating abbreviations explains each one.

Tile or flooring is F plus waste. Paint is W or WC times the coats. Baseboard is PF less the doorways. Drywall for a full room is WC. When a line is written as a formula over the room instead of a typed number, a change to the plan, such as a wall moved after the client changes their mind, reprices the bid without retyping it.

Allowances and Job Costs

Some costs aren't known until the client chooses: the vanity, the faucet, the tile itself. Put those in as allowances, a stated amount the client can go over or under, and say so on the bid. It keeps your number honest without pretending to know a fixture nobody has picked yet.

Then add the costs that belong to the job rather than to a room: the permit, the dumpster, floor and dust protection, and cleanup. They are easy to forget because they don't show on the plan, and they come straight out of your margin when you do.

Contingency, Overhead and Profit

Contingency covers waste and the surprises you can reasonably expect, such as a little rot under a toilet flange. Keep it a stated percentage of the work so the client sees it.

Overhead pays for running the business (insurance, vehicles, office, estimating time) and profit is what the company earns for taking the job on. In insurance repair work the usual figures are 10% overhead and 10% profit, added when a job needs three or more trades, the general contractor's role being to coordinate them. Remodelers set their own markup from their own costs; whatever you use, apply it to the subtotal plus contingency, and list it as its own line so the bid is easy to compare. Our guide to overhead and profit and the three-trade rule goes into it.

A Worked Example: a Hall Bathroom

Take a 5 by 8 foot hall bathroom with an 8 foot ceiling and one 30-inch door. From the plan: F = 40 SF, C = 40 SF, PF = 26 LF, and the walls are 208 SF before openings, about 191 SF after the door.

The client wants the floor tiled, a new vanity and toilet, and fresh paint. The lines follow from the measurements: tile 40 SF plus waste, paint WC, about 231 SF, at two coats, baseboard 26 LF less the 2.5 ft doorway, so 23.5 LF; a vanity and a faucet as allowances; the toilet set as each; demolition; and the permit and dumpster. That job takes tile, painting, finish carpentry and plumbing, four trades, so overhead and profit apply: on a subtotal plus contingency of $10,000, 10% and 10% add $1,000 each.

Writing It in vPlan AR

In the web editor, the Scope tab holds three separate estimates; Remodel is the one for work a client asks for, with no damage language. Add the rooms in the job, write the work requested for each, and add lines from the Remodel pack (demolition, cabinets, countertops, tile, fixtures, electrical and plumbing, permit and dumpster allowances) or from your own rate card. Line quantities can be formulas such as F, W or PF, so they follow the plan. Draft with AI can write a first version from the work requested and the finishes chosen for each room.

Export it as a Remodel Estimate in PDF, CSV or Excel. Overhead and profit are 10% and 10% by default, applied automatically at three or more trades, and the estimate lists the trades it counted; change the percentages in Settings → Estimate Rate Card, and include or leave them out for any bid. The starter rates are rough US figures, so replace them with yours before a bid goes out. The Remodel estimate is on Pro and Business. Watch it done on a kitchen remodel and a bathroom with allowances, or see the contractors page.

Frequently Asked Questions

How do you estimate a remodel?

Measure every room the work touches, write the client's requests room by room, turn each into line items in the order the work happens, take each quantity from the measurements (floor area, wall area less openings, perimeter), add allowances for fixtures the client hasn't chosen and job costs such as the permit and dumpster, then add contingency, overhead and profit.

What overhead and profit should a remodel estimate use?

Insurance repair work usually uses 10% overhead and 10% profit when a job needs three or more trades. Remodelers set their own markup from their costs. Whatever you use, apply it to the subtotal plus contingency and show it as its own line.

Should a remodel bid include allowances?

Yes, for anything the client hasn't chosen yet, such as the vanity, faucet or tile. State each allowance amount on the bid so the client knows the price changes if they choose something above or below it.

How do I calculate tile and paint quantities from a floor plan?

Tile or flooring is the floor area (F) plus waste. Paint is the wall area less doors and windows (W), or walls plus ceiling (WC), times the number of coats, divided by the coverage on the can. Baseboard is the floor perimeter (PF) less the doorways.